Project Overview

This project removed two culverts that were blocking access to 7.5 miles of good salmon spawning and rearing habitat and replaced them with a bridge.

We identified this project in 2006 and completed a habitat assessment and geotechnical soils testing to provide design data. The design was completed in January 2008. Permitting, which requires a biological evaluation, was started in February 2008. In addition, we completed the funding application.

All permits were received by November 2008, and we received funding on December 11, 2008.

Skidmore Slough
Skidmore Slough culverts
RSI
The completed bridge

Project Expenditures

Task Start Completed Budgeted Actual
Habitat Assessment Feb 2006 Mar 2006 $008,507 $008,502
Geotechnical Soils Test Mar 2006/Jul 2007 Jun 2006/Aug 2007 3,200 3,200
Biological Evaluation Feb 2008 Mar 2008 7,550 6,650
Design Feb 2007 Jan 2008 15,269 15,269
Construction Jul 2009 Sep 2009 643,325 643,325